TCN Restores Power Supply To Zamfara

The Transmission Company of Nigeria (TCN) has restored power supply to Zamfara State, having completed the replacement of glass insulators with silicone polymers insulators on a section of its 132kV Funtua-Gusau Transmission Line.

This was contained in a statement signed by the company’s general manager, Public Affairs, Ndidi Mbah, and posted on TCN’s Twitter handle on Thursday.

The maintenance work was earlier scheduled to take place from Friday, July 29th to Saturday, August 27th, 2022 from 9:00am to 5:00pm daily as announced by the Kaduna Electric which supplies the state electricity.

“In view of the associated inconvenience to electricity consumers, however, TCN engineering crew worked assiduously and were able to replace all insulations on 22 towers within five days, restoring power supply to all affected areas on August 2nd, 2022, the statement said.